Most popular anyang Linzhou zhenchen heavy industr

2022-08-13
  • Detail

Anyang Linzhou zhenchen heavy industry: build the world's most advanced drilling rig

anyang Linzhou zhenchen heavy industry: build the world's most advanced drilling rig

China Construction machinery information

Guide: Linzhou zhenchen heavy industry equipment manufacturing Co., Ltd. seized the golden time of the current project construction, scientifically arranged the construction force, and spared no effort to speed up the project, and the kilometer drilling rig project was progressing smoothly. The kilometer drilling rig project is jointly constructed by zhenchen heavy industry equipment manufacturing Co., Ltd. and Zhejiang Jiuhong Investment Co., Ltd

Linzhou zhenchen heavy industry equipment manufacturing Co., Ltd. seized the golden hour of current project construction. 1. Between mechanical properties, scientifically arrange construction forces, and spare no effort to speed up the project. The kilometer drilling rig project is progressing smoothly

The

kilometer directional drilling rig project is jointly constructed by zhenchen heavy industry equipment manufacturing Co., Ltd. and Zhejiang Jiuhong Investment Co., Ltd. with a total investment of 430million yuan. The kilometer directional drilling rig produced by this project is the most advanced drilling rig in the world at present. With GDS guiding system, it can drill to the designated position according to the pre-designed drilling trajectory through the computer detection outside the hole. It has unparalleled advantages in gas drainage, coalbed methane development, emergency rescue, detection and drainage of gob ponding and address structure, and its overall performance is at the international leading level. The project adopts world-class technical equipment, and the key parts are composed of guiding system, drill bit and drill pipe. The product has superior performance and high guiding accuracy

up to now, the project investment has completed 155 million yuan, the project filing has been completed, the plant enclosure has been enclosed, the plant road has been hardened, and the steel structure works of two standardized plants with a total area of more than 32500 square meters have been completed. At present, the ground hardening in the plant is under way, and the office building, staff canteen and other auxiliary projects are in progress simultaneously, but some domestic aluminum enterprises with technical strength have begun to promote related projects

xiaojunmin, general manager of Linzhou zhenchen heavy industry equipment manufacturing Co., Ltd.: "In the next step, zhenchen heavy industry equipment manufacturing Co., Ltd. should actively respond to the new situation in the macro-economy of the coal industry this year, thoroughly implement the 10 anti crisis measures determined at the beginning of the year, and ensure that the sales revenue this year exceeds 200million yuan. The four major varieties and ten series of drilling machine products will be put on the market to fill a gap in China. The output of 100 units will be achieved within the year, and the fixed asset investment this year will be 100million yuan."

for the kilometer drilling rig project, we should further speed up the progress of the new plant area project, scientifically allocate the construction force according to the project construction account, reverse the construction period, and cross promote. The phase I project strives to complete the civil works by the end of March and put into production in the middle of April. At the same time, we should speed up the preparatory work for the second phase of the project and strive to start construction in an all-round way by the end of September. Through the operation of new projects, we will do a good job in the transformation and upgrading of product projects, improve market competitiveness, and strive to promote our drilling rig products to the whole country within three years, so as to make due contributions to the construction of a central city at the junction of three provinces

it is understood that after the completion of the demonstration drilling rig project of promoting independent innovation by kilometer, it can produce 30 kilometer directional drilling rigs, 150 anchor drills and 170 gas drainage machines per year. It is estimated that the annual output value will be 1billion yuan, and the annual profits and taxes such as experimental force and displacement in the process of central point testing will be 160million yuan